Ascent Education Home
• CAT 2016 Classes
• TANCET 2016 Classes @ Chennai
• XAT 2016 Classes @ Chennai
• TANCET Y! Groups
• GRE-GMAT
• US B Schools
• Faculty List
• Question A Day

Ratio and Proportion - Quant/Math - CAT 2013

  1. Algebra
  2. Progressions
  3. Averages
  4. Clocks and Calendars
  5. Data Sufficiency
  6. English Grammar
  7. Function
  8. Geometry
  9. Coordinate Geometry
  10. Interest
  11. Mensuration
  12. Mixtures & Alligations
  13. Number System
  14. Percentages
  15. Permutation & Combination
  16. Pipes & Cisterns And Work & Time
  17. Probability
  18. Profit & Loss
  19. Races
  20. Ratio, Proportion
  21. Speed, Time & Distance
  22. Trigonometry
  23. Miscellaneous
  24. General Knowledge
Question 4 the day: March 26, 2003

The question for the day is from the topic of Ratio and Proportion
A group of workers can do a piece of work in 24 days. However as 7 of them were absent it took 30 days to complete the work. How many people actually worked on the job to complete it?

(1) 35 (2) 30
(3) 28 (4) 42
Correct Answer - (3)

Solution:


Let the original number of workers in the group be 'x'

Therefore, actual number of workers = x-7.

We know that the number of manhours required to do the job is the same in both the cases.

Therefore, x (24) = (x-7).30

24x = 30x - 210

6x = 210

x = 35.

Therfore, the actual number of workers who worked to complete the job = x - 7 = 35 -7 = 28.